We have reviewed your inquiry. Masking and capping of open fluid lines and electrical connectors is not included in any R&I or R&R operations relating to the cooling system or the electrical system. If needed, the estimate preparer should add the operation manually.


Inquiry type Missing Information
Area of Vehicle Front
Issue Summary Is masking & capping of open fluid lines and electrical connectors included in any R&I / R&R Operations relating to cooling system, electrical system components?
Suggested Action Is masking and capping off fluid lines and connectors ever included in any operation?