Inquiry:

19876

SubmittedStatus
2022-03-24 00:00:00 Resolved (No IP Change)

YearMakeModelBody
2021 Tesla Y Crossover

Tracking # 19876
Resolution

Estimated Release Date: Closed
Proposed Resolution: MOTOR stated:
After review, of your concern, we have determined the following:

• Gathering tools and equipment to complete a procedure is included in the estimated work time provided.

• Testing equipment and set up of equipment is not an included operation.


Inquiry type All Other
Area of Vehicle Electrical
Issue Summary Is time for "High Voltage PPE Prepare, Test, Put Away" included with "High voltage system deactivate/activate"This step is not listed in any OEM procedure we have seen, but is always listed within any HV training for the manufacture.Based on 910.137 - Electrical Protective Equipment - Glove must be tested daily, or before use.Then the OEM procedure can begin
Individual Procedure Steps Retrieve gloves, over leather gloves, safety hook, and glove tester. Prep your person - Remove all metallic objects, non cotton clothing, non-rated footwear, etc.Visually inspect gloves.Install gloves onto glove tester and check for any signs of damage or leaks.You will need a helper to have the safety isolation hook standing by as well.
Actual time to complete (min) 12
Suggested Action This item is needed for all HV operations. It could be needed on more than one day per vehicle (initial blueprinting, new part installation, etc.)However there should be an established time listed under Electrical> Additional Operations. it should be .8 to 1.0 hours Mechanical.